How Much Concrete Do I Need? A Guide for Slabs, Footings and Posts

Ordering the right amount of concrete saves money and avoids the worst outcome of any pour: running short halfway through. This guide shows how to work out the volume for the most common DIY projects, how to convert it into bags or a ready-mix order, and how much extra to allow.

The basic formula

Concrete is sold by volume. For a rectangular slab, multiply length × width × thickness, with every measurement in feet, to get cubic feet. Divide by 27 to get cubic yards, the unit ready-mix suppliers use.

The step people get wrong is the thickness: slabs are measured in inches, so divide by 12 first. A 4 inch slab is 4 ÷ 12 = 0.333 ft thick.

Example: a 10 × 10 ft patio, 4 inches thick, is 10 × 10 × 0.333 = 33.3 cubic feet, or 1.23 cubic yards. With 10% extra for uneven ground and spillage, order about 1.36 cubic yards. Our concrete calculator does this math for slabs, footings, columns and steps.

How thick should a slab be?

  • Walkways, patios and shed floors: 4 inches is the usual minimum.
  • Driveways for passenger cars: 4 to 5 inches; 6 inches or more for trucks, RVs or heavy equipment.
  • Hot tub pads and garage floors: often 5 to 6 inches, depending on the load.

Local building codes and soil conditions can require more, so check before you pour anything structural. Every extra inch on a 10 × 10 slab adds about 0.31 cubic yards.

Post holes and round columns

For a round hole or a tube form, the volume is π × radius² × depth. A 10 inch diameter hole that is 3 ft deep holds about 1.6 cubic feet — almost three 80 lb bags. Remember that the post itself takes up some of the space, so a little less concrete is needed than the empty hole holds.

See the concrete calculator (column mode) or our fence calculator, which counts posts for a whole fence line.

Bags or ready-mix?

Pre-mixed bags are convenient for small jobs. Typical yields are about 0.30 cu ft for a 40 lb bag, 0.45 cu ft for 60 lb and 0.60 cu ft for 80 lb. That 1.36 cubic yard patio would take about 62 bags of 80 lb — more than 2.4 tons of concrete to lift and mix by hand.

As a rule of thumb, once a pour reaches about 1 cubic yard, a ready-mix truck is usually faster and more consistent, even with a short-load fee. For anything in between, some suppliers rent towable mixers.

How much extra to order

Add 5 to 10% to the calculated volume. Forms bow slightly, the subgrade is never perfectly flat and some concrete always stays in the wheelbarrow or the chute. Running short on a ready-mix pour means a second truck and a cold joint, which costs far more than a little surplus.

Don’t forget the base and reinforcement

Most slabs sit on 4 inches of compacted gravel, which you can size with the gravel calculator. Rebar or wire mesh helps control cracking; the rebar calculator lays out a grid and counts the bars. If you would rather hire it out, the concrete patio cost calculator and driveway cost calculator show typical installed prices.

Frequently asked questions

How many bags of concrete are in a cubic yard?

A cubic yard is 27 cubic feet, so it takes about 45 bags of 80 lb (0.60 cu ft each), 60 bags of 60 lb or 90 bags of 40 lb.

How much concrete do I need for a 10 × 10 slab?

At 4 inches thick, a 10 × 10 ft slab needs 1.23 cubic yards, or about 1.36 cubic yards with 10% extra.